Question
Aman and Bhuvan can complete a work in 21 days together, while Bhuvan alone can do it in 35 days. If the ratio of efficiencies of Aman and Chintu is 2:3, find the ratio of efficiencies of Bhuvan and Chintu.
More Time and work Questions
- ‘m’ painters can paint a house in 60 days. If the crew increased by 25 painters, they could finish in 40 days. What is the value of ‘m’?
- A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 15 days, and A and C together can complete it in 2...
- Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion of ...
- ‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much per...
- ‘A’ and ‘B’ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the work for whic...
- 20 women can complete a task in 10 days by working 6 hours per day. How many women are required to complete the task in 5 days by working 8 hours per day?
- "Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but Bhanu stops after 4 days, a...
- 'X', 'Y', and 'Z' can complete a job individually in 20 days, 30 days, and 24 days respectively. 'Y' and 'Z' begin the task together. After 6 days, 'Z' lea...
- A and B together, B and C together and A and C together can complete a piece of work in 12 days, 11 days and 12 days respectively. Find the ratio of the ef...
- Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' and...