Question
A and B can finish a job in 10 and 15 days respectively.
They start together, but after 2 days A leaves. How many more days will B take to complete the rest?Solution
ATQ,
Work done in 2 days = 2(1/10 + 1/15) = 2(1/6) = 1/3. Remaining = 2/3. B alone rate = 1/15 ⇒ time = (2/3)/(1/15) = 10 days.
What is the theme for the International Day of Democracy 2025?Â
Which of the following is the most volatile foreign capital?
What is the limit on the amount of money for trade related transactions under RDA?
Which of the following is correct about regulation of commodity derivates in India?
i. Forward Market Commission is merged with SEBI for bette...
_____________ is the process usually accelerated by the roll up merger.
Which of the following is a stock variable?
Which among the following is/are the area(s) of operation regarding which complaints can be received by the Banking Ombudsman?
What is the total outlay of the PM-DevINE scheme for the period 2022-23 to 2025-26?
Match the following Five year Plans with their events
           Five Year Plans                      Events ...
Which is the first Indian company to be listed in NASDAQ?