Question
20 men working 6 hours a day can paint a building in 25
days. If 30 men work 8 hours a day, how many days will it take to paint the building?Solution
ATQ,
Let the efficiency of a man = 'x' units/hour
Total work = 20 × x × 6 × 25 = 3000x units
Number of days taken by 30 men working 8 hours/day =
= 3000x ÷ (30 × x × 8)
= 3000x ÷ 240x = 12.5 days
What happens to the shares of an Indian insurance company upon the appointed day according to the General Insurance Business (Nationalisation) Act?
When can a principal revoke an agent's authority?
As per the IRDA Act who constitutes the Authority, and what qualifications are required for its members?
Who can the policyholder nominate to receive the money secured by a life insurance policy in the event of their death, and what happens if the nominee ...
What is Axle weight?
What is an adapter vehicle?
Under the Insurance Act, 1938, the minimum paid-up capital required for starting a life insurance company is:
The Authority with the previous approval of the Central Government shall constitute an Advisory Committee consisting of _______________
What is the composition of the Insurance Advisory Committee, and what interests do its members represent?
The Motor Vehicles Act was enacted in the year: