Question
20 men working 6 hours a day can paint a building in 25
days. If 30 men work 8 hours a day, how many days will it take to paint the building?Solution
ATQ,
Let the efficiency of a man = 'x' units/hour
Total work = 20 × x × 6 × 25 = 3000x units
Number of days taken by 30 men working 8 hours/day =
= 3000x ÷ (30 × x × 8)
= 3000x ÷ 240x = 12.5 days
As per S.5 of the Indian Evidence Act, 1872 evidence can be given of the_________.
Under the SARFAESI Act, 2002, an appeal against the order of the Debt Recovery Tribunal (DRT) lies with:
Right to lodge caveat has been provided in which Section of the Code of Civil Procedure, 1908.
When is an interest in property considered "vested" under the transfer of property rules?
According to Section 12 of the Limitation Act, how is the period of limitation calculated?Â
What does "relevant geographic market" refer to?Â
Which statement is correct relating to debentures issued by a company___________
Under the Limited Liability Partnership Act, how can a firm convert into a limited liability partnership?
Section 268 empowers the Magistrate to discharge the accused:
The State shall not confer a title on any citizen or non-citizen except: