Question
A can do a work in 15 days, B in 20 days. They start
together, but A leaves after 4 days. In how many days is the work completed?Solution
ATQ, (A+B) rate = 1/15 + 1/20 = (4+3)/60 = 7/60 Work in 4 days = 4×7/60 = 28/60 = 7/15 Remaining = 1 − 7/15 = 8/15 B’s rate = 1/20 Time for remaining = (8/15)/(1/20) = (8/15)×20 = 160/15 = 10 2/3 days Total time = 4 + 10 2/3 = 14 2/3 days
What is the name of the joint initiative by iDEX and AFMS to promote medical advancements?
Which country recently introduced new banknotes featuring hologram portraits?
What is the main reason behind Zimbabwe's plan to launch a digital currency backed by gold reserves?
How many entrepreneurs has GAME supported since its inception in 2018?
Who is the author of the book “On Board My Years in BCCI”?
Which panel discussion at the 3rd International Conclave focused on adoption of the UNCITRAL Model Law?
Which IT company has partnered with high-tech industry giant Siemens AG to modernise its IT landscape worldwide and power cloud-led digital transformation?
Which country recorded the highest number of disaster displacements in 2022 according to the Global Report on Internal Displacement 2023 (GRID-2023)?
Who is responsible for the Ministry of Road Transport & Highways?
Dubai opened the 'Infinity Bridge' for traffic for the first time. Why the bridge is named 'Infinity Bridge'?