    Question

    β€˜P’ can complete a project in 12 days. β€˜Q’ is

    40% less efficient than β€˜P’. Working together, β€˜P’, β€˜Q’ and β€˜R’ can finish the job in 5 days. In how many days will β€˜R’ finish the job working alone?
    A 15 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 12 days Correct Answer Incorrect Answer
    D 24 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Time taken by β€˜P’ to complete the whole work alone = 12 days Time taken by β€˜Q’ to complete the whole work alone = 12 / 0.6 = 20 days Let the total work = 60 units (L.C.M of 12 and 20) Efficiency of β€˜P’ = 60 / 12 = 5 units/day Efficiency of β€˜Q’ = 60 / 20 = 3 units/day Let the efficiency of β€˜R’ be x units/day According to the question, (5 + 3 + x) Γ— 5 = 60 Or, 5x = 60 – 25 – 15 Or, x = 20 / 5 = 4 units/day Time taken by β€˜R’ to complete the whole work alone = 60 / 4 = 15 days