Question
βPβ can complete a project in 12 days. βQβ is
40% less efficient than βPβ. Working together, βPβ, βQβ and βRβ can finish the job in 5 days. In how many days will βRβ finish the job working alone?Solution
ATQ,
Time taken by βPβ to complete the whole work alone = 12 days Time taken by βQβ to complete the whole work alone = 12 / 0.6 = 20 days Let the total work = 60 units (L.C.M of 12 and 20) Efficiency of βPβ = 60 / 12 = 5 units/day Efficiency of βQβ = 60 / 20 = 3 units/day Let the efficiency of βRβ be x units/day According to the question, (5 + 3 + x) Γ 5 = 60 Or, 5x = 60 β 25 β 15 Or, x = 20 / 5 = 4 units/day Time taken by βRβ to complete the whole work alone = 60 / 4 = 15 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?