βPβ can complete a project in 12 days. βQβ is
40% less efficient than βPβ. Working together, βPβ, βQβ and βRβ can finish the job in 5 days. In how many days will βRβ finish the job working alone?Solution
ATQ,
Time taken by βPβ to complete the whole work alone = 12 days Time taken by βQβ to complete the whole work alone = 12 / 0.6 = 20 days Let the total work = 60 units (L.C.M of 12 and 20) Efficiency of βPβ = 60 / 12 = 5 units/day Efficiency of βQβ = 60 / 20 = 3 units/day Let the efficiency of βRβ be x units/day According to the question, (5 + 3 + x) Γ 5 = 60 Or, 5x = 60 β 25 β 15 Or, x = 20 / 5 = 4 units/day Time taken by βRβ to complete the whole work alone = 60 / 4 = 15 days
Viral disease transmitted by seed is
What is the outlay for the National Mission on Edible Oils - Oilseeds (NMEO-Oilseeds) for the period 2024-25 to 2030-31?
Under BPKP, financial assistance of Rs _____ /ha for 3 years is provided for cluster formation, capacity building and continuous handholding by trained ...
The PM KISAN aims to provide a payment of Rs. ______ /- per year, in ____ monthly instalments of Rs. 2000/- to the farmers families, subject to certain ...
Maximum profit is obtained at the point, where:
The term βPedagogyβ literally means ______
Days required for transplanting rice seedlings under dapog nursery is:
Cell division continues till maturity in fruit development of
The major activities of agricultural extension division are..?
In 1986 which first transgenic virus resistant plant was produced using virus resistance gene, which generates resistance against virus attack.