Question

Number of days taken by ‘P’, ‘Q’ and ‘R’ to do a certain work alone is (x + 4) days, (x - 11) days and (x - 1) days, respectively and number of days taken by ‘P’ and ‘Q’ together to do the work is (1/4) days more than the number of days taken by ‘Q’ and ‘R’ together to do the work. Find the number of days taken to complete the work if all three of them decided to do the work alternatively till the work gets completed starting with ‘P’, then ‘Q’ and then ‘R’.

A (x - 4) days
B (x - 5) days
C (x - 6) days
D (x - 7) days
E (x - 8) days
Practice Next

More Time and work Questions

Hey! Ask a query