Question
Time taken by 'A' to complete a work is 12 days less than that taken by 'B' to complete the same work. On working together, they can complete the work in 8 days. Find the time taken by 'A' to complete the work.
More Time and work Questions
- Two workers, ‘X’ and ‘Y’, can finish a job in 25 days together. If ‘X’ is 25% more efficient than ‘Y’, find the number of days ‘Y’ alone would take to comp...
- X can do a piece of work in 22 days. He worked at it for 11 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
- A can finish a job in 24 hours while B can finish it in 16 hours. If C is 50% more efficient than A and B together, then find the time taken by C alone to ...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- 15 men can finish a job in 24 days, while 36 women can do the same job in 20 days. How long will 1 man and 1 woman take to complete the work together?
- Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but Rahul left after 3 days. H...
- ‘A’ alone can complete a work in 15 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 5 days, then the remaining work...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1408, then fin...
- 'Rahul', 'Amit', and 'Vikram' together can complete a work in 20 days. 'Rahul' and 'Amit' together can complete the same work in 60 days. 'Vikram' alone ca...
- Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Determ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)