πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      'S' alone does a work in 18 days. 'T' is 50% more efficient

      than 'S'. Both work together but 'S' leaves after 6 days. Find the number of days 'T' will take to finish the remaining work.
      A 10 days Correct Answer Incorrect Answer
      B 2 days Correct Answer Incorrect Answer
      C 18 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let efficiency of 'S' = '6x' units/day

      Efficiency of 'T' = 6x Γ— (1.5) = 9x units/day

      Total work = 6x Γ— 18 = 108x units

      Work done in 6 days = (6x + 9x) Γ— 6 = 90x units

      Remaining work = 108x - 90x = 18x units

      Time by 'T' = 18x Γ· 9x = 2 days

      Practice Next
      More Time and work Questions
      ask-question