Question
A and B can complete a task together in 16 days, while B
alone takes 32 days to finish it. A began working alone and left after βxβ days, after which B completed the remaining work in 24 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 32 units
Efficiency of (A + B) = 32/16 = 2 units/day
Efficiency of βBβ = 32/32 = 1 unit/day
Amount of work done by βBβ = 24 Γ 1 = 24 units
Percentage of work done by βAβ = {(32 β 24)/32} Γ 100 = 25%
What is the life span of RBC?
The Doppler Effect occurs in:
In Youngβs double-slit experiment, dark fringes on the screen occur where:
Which one among the following statements is not true for Mammals?
Non-vascular plants do not contain:
According to a recent study, Groundwater in India is contaminated by which element?
What is the boiling point of pure water at normal atmospheric pressure (sea level)?
Up to what temperature can a mercury thermometer measure?
A car travels 150 kilometers in 3 hours. What is its average speed?
A piece of wood is held under water. The up thrust on it will be: