      Question

      A man, a woman and a boy can do a work in 3, 2, 6 days

      respectively. How many children were required with 1 man and 1 woman to complete the same work in 1/2 day?
      A 6 Correct Answer Incorrect Answer
      B 3 Correct Answer Incorrect Answer
      C 8 Correct Answer Incorrect Answer
      D 4 Correct Answer Incorrect Answer
      E 7 Correct Answer Incorrect Answer

      Solution

      Work done by a man in 1/2 days = 1/6 part Work done by a woman in 1/2 days = 1/4 part Work done by a boy in 1/2 days = 1/12 part Let one man and one woman together can do a piece of work in 1/2 days = No. of x children required According to the question, 1/6 + 1/4 + 1/12 = 1 (2 + 3 + x )/12 = 1 5 + x = 12 x = 12 – 5 = 7 Hence, 7 boys will be required.