Question
‘C’ and ‘D’ can complete a piece of work together in 24 days. If ‘C’ alone can complete it in 40 days, how long would ‘D’ take to do the same work alone?
More Time and work Questions
- Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the remaini...
- A can complete a work in 20 days and B can complete it in 30 days. They work together for 6 days, then B leaves. In how many total days will the work be co...
- Peter and Rachel can complete a project together in 20 days. Peter takes four times as long as Rachel to complete the same project alone. Find the time tak...
- "'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to finis...
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 20 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before comp...
- 'Sunil', 'Arjun', and 'Rahul' can complete a task individually in 45, 60, and 90 days respectively. All began the work together, but Sunil and Arjun left 1...
- 'A' alone can do some work in 18 days. 'B' is 20% more efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to ...
- 30 men can complete 3/5 part of a work in 8 days working 18 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 30...
- A pipe can fill a tank in 14 hours, and B pipe can drain a tank in 21 hours. If a system of N pipes (fill pipes and drain pipes put together) can fill the ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt