Question
‘C’ and ‘D’ can complete a piece of work
together in 24 days. If ‘C’ alone can complete it in 40 days, how long would ‘D’ take to do the same work alone?Solution
ATQ,
Let the total work be 120 units. {LCM (24 and 40)}
Combined efficiency of 'C' and 'D' = 120 ÷ 24 = 5 units/day
Efficiency of 'C' = 120 ÷ 40 = 3 units/day
Efficiency of 'D' = 5 - 3 = 2 units/day
So, time taken by 'D' alone = 120 ÷ 2 = 60 days
What should come in place of (?) question mark in the given number series.
81, 73, 66, 60, 55, ?
14 6 4 4 ? 48
...What should come in place of (?) question mark in the following number series.
5, 11, 23, 47, 95, ?
In each of the following number series, one term is missing. Find the missing term.
1, 4, 9, 16, 25, ?
What will come in place of the question mark (?) in the following series?
4, 11, 32, 95, 284, 851, ?
156, 182, 210, 240, 272, ?
31    32      35      ?      47       56
...What should come in place of (?) question mark in the following number series.
1, 2, 6, 24, 120, ?
What value should come in the place of (?) in the following number series?
71, 72, 76, 103, ?, 244254, ?, 1022, 1150, 1214, 1246