‘C’ and ‘D’ can complete a piece of work
together in 24 days. If ‘C’ alone can complete it in 40 days, how long would ‘D’ take to do the same work alone?Solution
ATQ,
Let the total work be 120 units. {LCM (24 and 40)}
Combined efficiency of 'C' and 'D' = 120 ÷ 24 = 5 units/day
Efficiency of 'C' = 120 ÷ 40 = 3 units/day
Efficiency of 'D' = 5 - 3 = 2 units/day
So, time taken by 'D' alone = 120 ÷ 2 = 60 days
A user communicates with a computer with the help of:
Which of the following permanent database that has an entry for each terminal symbol
The component responsible for synchronizing operations using timing signals is _______________. Â
Which of the following file format is not a video file format?
 Recently who among the following was re-elected general secretary of the 20th Central Committee of the Communist Party of China (CPC)?
Which of these are examples of interpreted programming languages? Â
Pre-programmed formulas in MS Excel are called _______. Â
Which of the following technologies were used by third-generation computers?Â
________ is the highest priority interrupt capable of interrupting all software and non-vital hardware devices.Â
Which type of network mostly we build, when two or more branches of an Organisation, situated in different countries, are connected together using inter...