Question
A group of 16 women can complete a certain job in 48
days, working 7 hours each day. How many women would be required to complete the same job in 32 days, if they work 12 hours per day?Solution
Let the efficiency of a woman = 'x' units/hour
Then, total work = 16 X x X 7 X 48 = '5376x' units
So, number of women required to complete the same job in 32 days working 12 hours a day
= 5376x Ă· (32 X 12) = 14
Which city has been notified as the sole capital of Andhra Pradesh?Â
What is the development window provided under the SASCI scheme for iconic tourist destinations?Â
ADB, India sign $350 million loan to expand metro rail network in which city?
What is the key theme of the 7th Rashtriya Poshan Maah 2024, observed by the Ministry of Women and Child Development?
What is the projected cargo capacity of the Vadhvan Port by 2029?
India’s first commercial Gallium Nitride (GaN)-based Mini/Micro LED display facility approved under ISM 1.0 will be set up by:Â
Under SEBI’s new rules, what is the upper ceiling for determining materiality of Related Party Transactions (RPTs)?Â
What is the purpose of the IEPFA’s “Saksham Niveshak” campaign?Â
Which city was ranked as the world’s most polluted city in the 2024 Air Quality Index Report?
- Which chili variety from Telangana received the GI tag recently?