Question
P and Q can do a piece of work in 32 and 40 days
respectively. They began to work together but P leaves after sometimes and Q completed remaining work in 16 days. After how many days did P leaves (in days)?Solution
Let P worked for x days. According to question, ⇒ x/32 + (x+16)/40 = 1 ⇒ (5x+4(x+16))/160 = 1 ⇒ 5 x + 4x + 64 = 160 ⇒ 9x = 160 – 64 = 96 ⇒ x = 96/9 = 32/3 = 10(2/3) days P left the work after 10(2/3) days.
What is the interest rate on GOI Floating Rate Bonds, 2035 (GOI FRB 2035) for the period January 25, 2025, to January 24, 2030?
Who won the IAA Golden Compass Award at the 45th IAA World Congress?
Which private sector insurer , is set to incorporate a not-for-profit company for housing the Bima Sugam platform - ‘Rashtriya Bima Sugam Nigam’ the...
Where are the headquarters of the Insurance Regulatory and Development Authority of India ?
What is the 'Best Airport Staff in India & South Asia 2024' award received by GMR Hyderabad International Airport based on?
What is the new category created by the Reserve Bank of India (RBI) for commercial banks as part of the revised investment norms?
Recently Arjun Babuta clinched the gold beating Lucas Kozeniesky . Which Sports he is associated with?
How much did China invest in the world's largest hydropower dam on the Brahmaputra River?
Which two entities are in a 50:50 joint venture for JioBlackRock Asset Management Pvt. Ltd.?
What is the purpose of the International Purple Fest – Goa 2024?