Question
Ravi can finish a task in 18 days. If Ravi and Rohan
work together, they can complete the task in 10 days. How many days would Rohan alone take to finish the work?Solution
ATQ,
Let the total work be 90 units {LCM (18 and 10)}
Efficiency of Ravi = (90/18) = 5 units/day
Efficiency of Ravi and Rohan together = (90/10) = 9 units/day
Efficiency of Rohan = 9 - 5 = 4 units/day
Time required by Rohan to complete the work alone = (90/4) = 22.5 days
Select the most appropriate direct form of the given sentence.
She exclaimed that she looked very ugly in that dress.
Select the correct indirect form of the given sentence.Â
The driver said to the passerby, “Do you know the way to the market?”
Choose the option that is the indirect form of the sentence.
“We are going to Tirupati next week,” Deepa told her friends.
Choose the option that is the direct form of the sentence.
Jai said that he wanted to be a soldier.
The manager said "Vivek must go tomorrow to meet the client".
My friend asked Ritesh whether he …………. knock at a stranger’s door.
She will never tell you the truth.
Select the option which correctly converts the given sentence into indirect speech.
You said to her, "I am feeling tired and want to rest now."
Select the most appropriate option expressed in indirect speech.
The doctor has given me a very painful injection.