πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      Ashish and Anil can do a piece of work in 10 days and 15

      days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete the remaining work.
      A 10.5 days Correct Answer Incorrect Answer
      B 4.5 days Correct Answer Incorrect Answer
      C 9 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 10 and 15) = 30 units Efficiency of Anil = 30/15 = 2 units/day Remaining work = 30 x 0.6 = 18 units Time taken by Anil to complete the remaining work = 18/2 = 9 days

      Practice Next
      ask-question