Question

Time taken by A and B together to complete a work is 1 day less than the time taken by B alone to complete the same work. With his half efficiency B can complete the work in 10 days. find the efficiency ratio of A to
B.

A 1:4
B 2:5
C 1:8
D 1:2
E None of these