Question
Time taken by A and B together to complete a work is 1
day less than the time taken by B alone to complete the same work. With his half efficiency B can complete the work in 10 days. find the efficiency ratio of A to B.Solution
ATQ,
B's full efficiency: B completes the work in 5days (since with half efficiency, B takes 10days). A and B together: Time taken = 5−1 =4 days. Combined efficiency of A and B = 1/4 work units/day. B's efficiency = 1/5 work units/day. A's efficiency: Efficiency ratio (A:B):
The efficiency ratio of A to B is 1:4 .
How many persons live below A (considering both types of flats)?
Which of the following combination is false?
Combination of ages of which pair is maximum?
If all the persons are arranged in alphabetical order from bottom to top, then how many persons remain unchanged in their positions?
In which of the following car more than thee person sits?
On which of the following floor does Vikrant lives?
Which of the following students did not opt for Physics?
Seven persons, Shikha, Garima, Nidhi, Pooja, Manisha, Neena and Anu, lives in a 7-storey building, but not necessarily in the same order. The bottommost...
Who celebrated his birthday in the beginning of the month?
What is the code of ‘work when’?