Question
Rahul, Rohit, and Raj alone can complete a project in
40, 80, and 120 days respectively. All of them started working together, but after 10 days, Rahul left the job, and 12 more days later, Rohit also left the job. So for how many days did Raj work?Solution
 Total work = LCM of 40, 80, and 120 = 240 units.  Rahul's daily work = 240/40 = 6 units.  Rohit's daily work = 240/80 = 3 units.  Raj's daily work = 240/120 = 2 units.  Work done in the first 10 days = 10 × (6 + 3 + 2) = 110 units.  Work done by Rohit and Raj together in the next 12 days = 12 × (3 + 2) = 60 units.  Remaining work = 240 - 110 - 60 = 70 units.  Time taken by Raj alone to complete the remaining work = 70/2 = 35 days.  Total days Raj worked = 10 + 12 + 35 = 57 days
Fertilizer which is present in granulated form and not in vapor form.
FRI ( forest research institute ) was established is located at
The movement and filtration of water through soils and permeable rock is termed as
What is the premium rate for rabi crops under PMFBY
Which of the following is correct in case of seedlings?
Which of the following is used as a purgative in animals?
Which of the following is an Open Sourced Software?
The optimum age of seedling for transplanting long duration rice varieties is
Under the given options, which of the following is the provision under NFSA 2013?Â
Agro-climatic zones in India are formed during