Question
Mohan, Sohan, and Rohan alone can finish a piece of work in 50, 100, and 150 days respectively. They start the work together, but Mohan leaves after 8 days and Sohan leaves 14 days after Mohan. How long did Rohan work?
More Time and work Questions
- Rohit is five times as efficient as Sohan and twice as efficient as Mohan. If Sohan takes 15 days to finish some work, then find the time taken by Rohit an...
- A can complete a work in 9 days , and B can complete it in 18 days . They work together with C and complete the work in 3 days . In how many days can C...
- There is enough food in a camp to last for 60 days if each of the 20 soldiers present at the camp eat 5 times a day. After 30 days, 10 more soldiers joined...
- When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, then...
- A alone can complete a piece of work in 18 days and B alone can do it in 24 days. They work together for 6 days, after which A leaves. In how many more day...
- A can complete a work in 20 days and B can complete it in 30 days. They work together for 6 days, then B leaves. In how many total days will the work be co...
- A team of workers can finish a task in 36 days. However, 5 workers leave the task every day, and it gets done in 48 days. Find the time needed for 90 worke...
- A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x − 2) units per day. They work together for 9 days and the r...
- Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will...
- A can complete a work in 12 days, and B can complete the same work in 18 days. How many days will they take to complete the work if they work together?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)