Question
βRβ and βSβ can complete an assignment in 72
days and 90 days respectively while βRβ, βSβ and βTβ together can complete the same assignment in 24 days. Find the time taken by βTβ alone to complete 30% of the work.Solution
ATQ Let total amount of work = 360 units (LCM of 72 and 90) Amount of work done by βRβ in one day = 360/72 = 5 units Amount of work done by βSβ in one day = 360/90 = 4 units Amount of work done by βRβ, βSβ and βTβ in one day = 360/24 = 15 units Amount of work done by βTβ in one day = 15 β 5 β 4 = 6 units Desired time = (0.30 Γ 360)/6 = 18 days
According to the 2011 census, which of the following states of India is the lowest sex ratio?
Which organization was established in response to the December 2004 Indian Ocean tsunami?
What is the name of antibiotic containing chlorine which is produced by soil containing microorganisms and is effective for the treatment of typhoid fever?
In India, cricket was brought by whom?
The request/reply protocol for exchanges on the internet network is called:
Consider the following statement about Center of Excellence (CoE) named ATMAN:
1. Full form of the ATMAN is Advanced Technologies for Monitoring ...
The crops sown during the winter season are called _____________ crops.
'Hardaul Katha' are folk songs typical to __________ which spreads over Uttar Pradesh and Madhya Pradesh
PM Mitra Mega Textile Park will be set up in how many states?
Who among the following was a saint from Maharashtra?