Question
βRβ and βSβ can complete an assignment in 72
days and 90 days respectively while βRβ, βSβ and βTβ together can complete the same assignment in 24 days. Find the time taken by βTβ alone to complete 30% of the work.Solution
ATQ Let total amount of work = 360 units (LCM of 72 and 90) Amount of work done by βRβ in one day = 360/72 = 5 units Amount of work done by βSβ in one day = 360/90 = 4 units Amount of work done by βRβ, βSβ and βTβ in one day = 360/24 = 15 units Amount of work done by βTβ in one day = 15 β 5 β 4 = 6 units Desired time = (0.30 Γ 360)/6 = 18 days
Which of the following agencies recently has been taken under the ambit of Integrated Ombudsman SchemeΒ
What is the maximum amount of deposits that can be accepted by Payment Banks?
Which of the following measures the time decay on option premium?
Which type of borrower is typically associated with Self-Help Groups (SHGs) in priority sector lending?
How much Viability Gap Funding can the Central Government provide for infrastructure projects under PPP?
The process in which certain types of assets are pooled so that they can be repackaged into interest-bearing securities is called:
The price of the Sovereign Gold Bond is fixed in Indian rupees is based on simple average of closing price of 999 purity gold of how many days?
Who was appointed as a first Chairman of Insolvency and Bankruptcy Board of India?
Observing changes in financial variables across the years is :
What is the Complaint redressal system of SEBI called