Question
βMβ is 60% more efficient than βNβ. βNβ
started the work alone and worked for 20 days and after that βNβ is replaced by βMβ. If the total work is completed in 25 days, find the time taken by βMβ to finish the same work alone?Solution
Let the efficiency of βNβ = β5xβ units/day Efficiency of βMβ = β8xβ units/day Time taken by βMβ to complete the remaining work = 25 β 20 = 5 days Total work = 20 Γ 5x + 5 Γ 8x = 140x units Desired time = 140x/8x = 17.5 days
Which bank has entered into a partnership with Aditya Birla Sun Life Insurance to provide insurance solutions to its customers?
Which of the following statements is/are not true regarding the proposed changes/changes being done by the Monetary Policy Committee?
I.The Reser...
Indian Grandmaster R Praggnanandhaa defeated world no.1 Magnus Carlsen, in the eighth round of the Airthings Masters online rapid chess tournament, beco...
Which of the following state has topped NITI Ayog’s Export Preparedness Index 2021?
Claude 3, recently seen in the news, is associated with which one of the following?
The first BIMSTEC Traditional Music Festival was held in which city?
What specific agreement have India and France made to enhance their cooperation in the Indian Ocean?
The government has mobilized a gross amount of Rs 5.77 lakh crore by issuing dated securities in the current financial year up to July 31, 2023. The cen...
How many sectors were identified in the World Bank's "Jobs at Your Doorsteps" study?
B S Patil recently sworn in as Lokayukta of which state?