Question
40 men can complete a piece of work in 48 days. ‘x’
men started the work and after 30 days 56 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’Solution
Total work = 40 × 48 = 1920 units According to question; 30 × x + 18 × (x + 56) = 1920 Or, 30x + 18x + 1008 = 1920 Or, 48x = 1920 Or, x = 40
Why was Kozhikode recently inducted into the WHO’s Global Network of Age-friendly Cities?
RBI lists how many rating agencies for banks' capital adequacy purposes?
Which of the following statements is/are true regarding the pilot programme for wholesale digital rupee in the call money market initiated by RBI?
<...An insurance claim of _______ has been transferred to the insured farmers of Rajasthan, Uttar Pradesh, Himachal Pradesh, Chhattisgarh, Uttarakhand and H...
Life Insurance Corporation of India (LIC) has ended up with a_______ stake in Jio Financial Services (JFS) with the insurer’s stake in JFS valued ...
What was the deflation rate in onion prices under primary food articles in September 2025 WPI data?
The third edition of the Indian Navy’s ‘MAHASAGAR’ virtual interaction was held under the leadership of which Indian Navy official?
What is the main feature of MuleHunter, launched by the RBI?
What is the revised deadline for completing the remaining phases of the Vizhinjam Seaport in Kerala?
Consider the following statements about the collaboration between IIIT and Kerala Kalamandalam:
1. The project aims to create an AI-enabled tool ...