Question
If A can complete a job in 15 days and B can complete the same job in 10 days, and they work together for 4 days before A leaves. How many more days will B take to finish the job alone?
More Time and work Questions
- There is enough food in a camp to last for 30 days if each of the 100 soldiers present at the camp eat 3 times a day. After 20 days, 50 soldiers left the c...
- ‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 30 hours. If ‘B’ completed the rest of the work in 2...
- 'P' and 'Q' together can complete the work in 12 days. 'Q' alone can complete the work in 36 days. If R is 50% more efficient than P, find the time taken b...
- 6 men and 2 boys together can complete a work in 15 days. 3 men and 5 boys can together complete half of the same work in 10 days. Find the time taken by 1...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
- In an office, an employee plans to do a work in 12 days with 4 laptops. But after 4 days, he found that only 40% of the work is done with the laptops worki...
- John does ½ piece of work in 3 hours, Joe does ¼ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How lon...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
- Sita is 50% more efficient than Simran. Working together, they finish the work in 24 days. How long will Sita take to complete the work alone?