Question

If A can complete a job in 15 days and B can complete the same job in 10 days, and they work together for 4 days before A leaves. How many more days will B take to finish the job alone?

A 3.33 days
B 6 days
C 7.5 days
D 5 days
Practice Next

More Time and work Questions

Hey! Ask a query