    Twenty laborers can complete a piece of work in 12 days.

    If 20 laborers started working and after 3 more days, additional laborers joined to complete the remaining work in 6 days, determine the number of laborers who joined after 3 days of the work started.
    A 15 Correct Answer Incorrect Answer
    B 12 Correct Answer Incorrect Answer
    C 25 Correct Answer Incorrect Answer
    D 10 Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let the number of Laborers joined after 3 days of the work started be β€˜a’. 20L Γ— 12 = 20L Γ— 3 + (20 + a) L Γ— 6 240L = 60L + 120L + 6aL 60L = 6aL a = 10