📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug âš¡ Enroll Now

    Question

    Twenty laborers can complete a piece of work in 12 days.

    If 20 laborers started working and after 3 more days, additional laborers joined to complete the remaining work in 6 days, determine the number of laborers who joined after 3 days of the work started.
    A 15 Correct Answer Incorrect Answer
    B 12 Correct Answer Incorrect Answer
    C 25 Correct Answer Incorrect Answer
    D 10 Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let the number of Laborers joined after 3 days of the work started be ‘a’. 20L × 12 = 20L × 3 + (20 + a) L × 6 240L = 60L + 120L + 6aL 60L = 6aL a = 10

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call