      Question

      Twenty laborers can complete a piece of work in 12 days.

      If 20 laborers started working and after 3 more days, additional laborers joined to complete the remaining work in 6 days, determine the number of laborers who joined after 3 days of the work started.
      A 15 Correct Answer Incorrect Answer
      B 12 Correct Answer Incorrect Answer
      C 25 Correct Answer Incorrect Answer
      D 10 Correct Answer Incorrect Answer
      E none of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let the number of Laborers joined after 3 days of the work started be ‘a’. 20L × 12 = 20L × 3 + (20 + a) L × 6 240L = 60L + 120L + 6aL 60L = 6aL a = 10