πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A can finish a job in 20 days while B can finish same

      job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have managed to complete the job. Find in how many days C alone can finish the job.
      A 9 days Correct Answer Incorrect Answer
      B 3 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 24 days Correct Answer Incorrect Answer

      Solution

      A's 1 day's work = 1/20 B's 1 day's work = 1/30 (A + B)’s 1 day's work = 1/20 + 1/30 = 1/12 (A + B)’s 5 day's work = 5/12 Remaining fraction of work after 5 days = 1 – 5/12 = 7/12 Let C's 1 day's work be 1/M. Then, β‡’ Β (1/12 + 1/M) = 7/12 Γ— 1/3.5 β‡’ Β (1/12 + 1/M) = 1/6 β‡’ Β 1/M = 1/12 C alone can complete the work in 12 days.

      Practice Next
      ask-question