Question
3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
More Time and work Questions
- Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Armaa...
- 50 children can decorate a hall in 25 days. If 25 children began decorating and after 10 days ‘z’ additional children joined, completing the decoration in ...
- Raj alone can complete a work in 25 days. Mohan is five times as efficient as Raj. Find the percentage of work completed by Raj and Mohan together in 5 day...
- Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constructed...
- 16 man can make a wall in 3 days. How many men required to complete the same work in 8 days ?
- 'P' completes a work in 18 days whereas 'Q' completes the work in 54 days. Both of them started the work together, but 'Q' left the work 6 days before the ...
- Working alone, B can complete the work in 25 days. C is twice as efficient as B and A takes 2.5 days more than it takes C to complete the work. Working tog...
- Mukta takes 8 hours less than Raj to complete the work, and Mukta also takes 32 hours less than Bheem to complete the same work. If Raj and Bheem start wor...
- X can do a piece of work in 26 days. He worked at it for 13 days and then Y finished it in 10 days. In how many days can X and Y together finish the work?
- 2 men and 4 boys can together complete a work in 6 days. 3 men and 1 boy can together complete the same work in 5 days. Find the time taken by 10 boys toge...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)