Question
3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
More Time and work Questions
- A worker finishes 40% of a job in 6 days. At the same rate, how many more days are needed to finish the remaining work?
- 24 delivery boys can complete a delivery in 15 days. If 12 boys start the same work, and after 12 days, 'd' more boys join the work, completing the remaini...
- ‘P’ takes 25 days to complete a piece of work. ‘Q’ is 25% more efficient than ‘P’. Find the time taken by them to complete 90% of the work together.
- P, Q and R take 18, 15 and 10 days respectively to complete a job. Compare their efficiencies as a ratio.
- A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
- A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same time during which the tank is fil...
- In how many days can ‘Q’ alone complete the work? I. P, Q and R together can complete the work in 9`(3)/(13)` days. II. P and Q together can complete t...
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...
- 'B' can complete a task in 15 days, and when 'A' and 'B' collaborate, they can finish the same task in 8 days. 'A' initiated the work alone and worked for ...
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘6a’ hours respectively. If they together can complete half of the work in 6 hours, then...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)