Question
A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the efficiencies of A, B and C, respectively.
More Time and work Questions
- A alone can complete a piece of work in 12 days and B alone can complete it in 18 days. They work together with C and complete the work in 4 days. In how m...
- A can complete a work in 20 days, B in 30 days and C in 60 days. They work together for 5 days, then C leaves. In how many more days will A and B finish th...
- Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient than ‘P1’ but takes 5 days les...
- A takes 15 days more than B to complete a piece of work. Working together, they can complete the work in 18 days. In how many days can B alone complete the...
- Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can Deepak...
- 2 men and 3 boys can do a piece of work in 405 days while 3 men and 2 boys can do the same work in 324 days. In how many days can 5 men and 5 boys do that ...
- P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work in 1...
- (x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. Find...
- Ajay and Vijay can finish a task in 9 days working together. Charu, who is twice as efficient as Vijay, can complete the task alone in 18 days. If Ajay and...
- Two efficient workers or three non-efficient workers can complete a certain task in 20 days. If each efficient worker improves their efficiency by 33(1/3)%...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)