Question
An elephant can do a work as fast as two horses ‘A’ and ‘B’ can do it by working together. If horse ‘A’ alone can complete the work in 38 hours and horse ‘B’ in 57 hours, then find the time taken by elephant to complete the work.
More Time and work Questions
- Rahul used to complete 25 problems in 50 minutes. But now, his efficiency has dropped by 20%. How much time will he need to complete the same number of pro...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &lsqu...
- Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by San...
- Ankit can complete a task in 16 days, while Bina alone can complete the same task in 24 days. Ankit starts the work alone and continues for 6 days. Then, B...
- ‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.1200, then fin...
- A, B, and C are three workers who can complete a certain piece of work. A alone can complete the work in 12 days. B alone can complete the same work in 3X ...
- A red JCB machine can complete the excavation of a field in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines op...
- A and B together can do a work in 5 days. If A can alone do the same work in 15 days, then in how many days B alone will do the same work?
- Ashish and Anil can do a piece of work in 20 days and 25 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the r...
- Rohan can do a piece of work in 30 days. Rohan with the help of Karan does the same piece of work in 20 days. If they are paid Rs 3696 for the work, then w...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt