Question
A can complete a piece of work in 16 days and B can complete it in 24 days. They work together for 4 days and then B leaves. In how many total days is the work completed?
More Time and work Questions
- 'R' can independently complete a task in 36 days, whereas 'S' can accomplish 40% of the same work within 16 days. 'S' starts the task solo and withdraws af...
- 'S' alone does a work in 18 days. 'T' is 50% more efficient than 'S'. Both work together but 'S' leaves after 6 days. Find the number of days 'T' will take...
- A and B can together complete a work in 8 days, B and C in 12 days, and C and A in 16 days. In how many days can C alone complete the work?
- Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it tak...
- ‘X’ and ‘Y’ together can complete a work in 8 days, while ‘Y’ and ‘Z’ together can complete the work in 5 d...
- There is enough food in a camp to last for 40 days if each of the 60 soldiers present at the camp eat 3 times a day. After 10 days, 10 soldiers left the ca...
- Sonal completed 30% of work alone and left the remaining work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find ...
- 15 men can finish a job in 24 days, while 36 women can do the same job in 20 days. How long will 1 man and 1 woman take to complete the work together?
- 'Meera', 'Kiran', and 'Suman' together can complete a work in 30 days. 'Meera' and 'Kiran' together can complete the same work in 90 days. 'Suman' alone ca...
- ‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 10 hours. If ‘B’ completed the rest of the work in 1...