Question
A can complete a piece of work in 16 days and B can complete it in 24 days. They work together for 4 days and then B leaves. In how many total days is the work completed?
More Time and work Questions
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- The efficiency of X is 50% of the efficiency of Y. If Y can type 180 pages in 45 days, then find the number of days taken by X alone to type 360 pages.
- A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece of...
- Priya completes 30% of a task in 9 days. Her efficiency is 50% greater than Meera's. How many days will it take for both Priya and Meera, working together,...
- Two people, A and B, working separately can sanitize a building in 6 and 10 hours, respectively. They work in stretches of one hour alternately. If A begin...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- Sudhanshu completes `1/3` of work in 12 days, then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neeraj alone t...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- 16 man can make a wall in 3 days. How many men required to complete the same work in 8 days ?
- A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)