Question
A' can finish a job in 24 days, while 'B' is 25% less
efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for them to complete 87.5% of the task?Solution
ATQ, Time taken by βBβ to complete the work = 24/0.75 = 32 days Let the total work = 96 units Efficiency of βAβ = 96/24 = 4 units/day Efficiency of βBβ = 96/32 = 3 units/day Work to be done = 0.875 Γ 96 = 84 units Work completed by βAβ and βBβ in 2 days = (4 + 3) = 7 units Therefore, to complete 84 units of work time required = 2 Γ (84/7) = 24 days
More Time and work Questions
- Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___ - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN