ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    тЪб Month End Offer - Flat 52% Off On All Courses! Enroll Now тЪб
    00:00:00 AM Left

    Question

    A' can finish a job in 24 days, while 'B' is 25% less

    efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for them to complete 87.5% of the task?
    A 10 days Correct Answer Incorrect Answer
    B 24 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Time taken by тАШBтАЩ to complete the work = 24/0.75 = 32 days Let the total work = 96 units Efficiency of тАШAтАЩ = 96/24 = 4 units/day Efficiency of тАШBтАЩ = 96/32 = 3 units/day Work to be done = 0.875 ├Ч 96 = 84 units Work completed by тАШAтАЩ and тАШBтАЩ in 2 days = (4 + 3) = 7 units Therefore, to complete 84 units of work time required = 2 ├Ч (84/7) = 24 days

    Practice Next
    More Time and work Questions
    ask-question