ATQ, Time taken by ‘B’ to complete the work = 24/0.75 = 32 days Let the total work = 96 units Efficiency of ‘A’ = 96/24 = 4 units/day Efficiency of ‘B’ = 96/32 = 3 units/day Work to be done = 0.875 × 96 = 84 units Work completed by ‘A’ and ‘B’ in 2 days = (4 + 3) = 7 units Therefore, to complete 84 units of work time required = 2 × (84/7) = 24 days