Question
A can complete a piece of work in 80 days, B takes 20% more
time than A to complete the same work while C takes 25% more time than B to complete the whole work. Find the time taken by all of them together to complete the whole work.Solution
Time taken by B to complete the whole work = 1.2 × 80 = 96 days
Time taken by C to complete the whole work = 1.25 × 96 = 120 days
Total work (let) = 480 units (LCM of 80, 96 and 120)
Efficiency of A, B and C is 6 units/day, 5 units/day and 4 units/day respectively
Desired Time = 480/15 = 32 days
Advance amount received from customers is not considered as sale. It is based on which concept?
Which report is issued after completion of statutory audit of a PSU?
An enterprise consumes 25,600 units of a component annually. The order cost is ₹600 per order, and carrying cost is ₹12/unit/year. A supplier offers...
The coefficient of correlation takes the value in which of the following ranges?
Which of the following is shown under investing activities in the cash flow statement ?
_______ refers to the information collected by an auditor to ascertain the accuracy and compliance of a company's financial statements.
Which accounting standard provides guidance on how to account for foreign currency transactions and the effects of changes in foreign exchange rates on...
Which of the following expenditure should NOT be recognized as intangible asset as per AS 26?
Under Ind AS 116, which of the following is true for lessees?
While finalizing the current year’s profit, the company realized that there was an error in the valuation of closing inventory of the previous year. I...