Question
A can complete a piece of work in 80 days, B takes 20% more
time than A to complete the same work while C takes 25% more time than B to complete the whole work. Find the time taken by all of them together to complete the whole work.Solution
Time taken by B to complete the whole work = 1.2 × 80 = 96 days
Time taken by C to complete the whole work = 1.25 × 96 = 120 days
Total work (let) = 480 units (LCM of 80, 96 and 120)
Efficiency of A, B and C is 6 units/day, 5 units/day and 4 units/day respectively
Desired Time = 480/15 = 32 days
Where was the Urban Co-operative Bank (UCB) situated, whose license was cancelled by the Reserve Bank of India (RBI) in Dec 2023?
Who was the first woman to receive the Arjuna award for Hockey?
Which of the following is a risk associated with implementation of green revolution in India?
I. It would Possibly increase the disparities betwe...
Which gas is responsible for the blue color of the Earth’s atmosphere?
Match the following states with their respective ranks at the Khelo India Youth Game 2023 and choose the correct code.
States Their Ranks
...
Who is the promoter of Funskool India Ltd., a company that has acquired the licence to manufacture and distribute action figures of Chhota Bheem and fri...
What is the minimum net worth of SRO Fintech?
Find a single discount percentage equivalent to successive discounts of 20%, 30%, and 35% ?
On May 23, 2023, who assumed the position of Chairperson at the Competition Commission of India?
The maiden international cruise vessel between Chennai and Sri Lanka was flagged off by the Union Minister of Ports, Shipping and Waterways Sarbananda ...