Question
A can complete a piece of work in 80 days, B takes 20% more
time than A to complete the same work while C takes 25% more time than B to complete the whole work. Find the time taken by all of them together to complete the whole work.Solution
Time taken by B to complete the whole work = 1.2 × 80 = 96 days
Time taken by C to complete the whole work = 1.25 × 96 = 120 days
Total work (let) = 480 units (LCM of 80, 96 and 120)
Efficiency of A, B and C is 6 units/day, 5 units/day and 4 units/day respectively
Desired Time = 480/15 = 32 days
Directions : In each of the questions given below a sentence is given with three words in bold. Choose the option which gives the correct sequence of t...
- In the questions given below, a sentence has been divided into four fragments (A), (B), (C) and (D) and is arranged (not necessarily in the correct order)....
Which of the following is the third sentence of the paragraph after rearrangement?
1.      It was
P. In keeping with my mood
Q. A soft summer evening
R. As I walked sedately
S. In the direction of new house
A. master plan is being amended, to
B. enforce the sealing, especially when the
C. courts should not yield to any pressure and
D. o...
The man was allowed
P. drain the fluid from his lungs
Q. to sit up in his bed
R. for an hour in the afternoon to help
Rearrange the parts of the sentence in correct order.
The rattlesnake
P. it has specialised Jacobson’s
Q. organs, which gives it ...
- Below are given a few sentences with their parts jumbled in a random order. Below the sentences are given possible rearrangements of the parts. You need to...
The most longer (A) element of the Court’s judgment was its proposition (B) that caste, and the ___________ (C) to right historical wrongs, is no cont...
Each question is divided into four parts a,b,c,d. In some questions they are not in the sequence so according to grammar and context re- arrangement is...