Question
If 15 women or 18 men or 12 boys can do a piece of work
in 18 days of 10 hours each, find how many boys assisted by 5 women and 6 men will finish the same work in 20 days of 6 hours each.Solution
Given, 15 women = 18 men = 12 boys So 5 woman =4 boys & 6 men=4 boys Now by chain rule, M1D1H1 =M2D2H2 So 12boys×18×10 = (Tboys+5women+4man×20×6 12boys×18×10 = (T +4+4)boys ×20×6 18 = T+8 or T = 10 Hence, 10 boys more are required.
Under Section 176(3) of the BNSS, 2023, for offences punishable with imprisonment of seven years or more, which of the following is a mandatory obligati...
Section 4 empowers the Central Government to:Â
First Information Report is mentioned under
What is the restriction on commission, brokerage, discount, etc., on sale of shares as per the Banking Regulation Act?
   Who is eligible for appointment as Governor?
In which year the provisions of Section 16-A which allow keeping of books in computer floppies diskettes was inserted in the Registration Act, 1908?
Under Section 4 of the Indian Trusts Act, 1882, Mr. U creates a trust deed providing: "I settle this property upon Trustee V in trust to support politic...
As per section 97 of the Companies Act, If any default is made in holding the annual general meeting of a company the ______________  may, call, or d...
The ______________________ may delist the securities, after recording the reasons therefor, from any recognised stock exchange on any of the ground or g...
A party can claim compensation for any loss or damage caused to him, by breach of contract, which____________________