Question
U and V individually can complete a work in 45 days and 90 days respectively. If the time taken by W alone to complete the work is 0.8 times the time taken by U and V together to complete the work, find the time taken by W to complete the work while working alone.
More Time and work Questions
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 6 ti...
- ‘A’ is 25% less efficient than ‘B’, and ‘C’ is 75% more efficient than ‘B’. All three together complete a task in 32 days. After ‘A’ and ‘B’ work together ...
- ‘A’ alone can complete a work in 15 days while ‘A’ and ‘B’ together can complete the same work in 10 days. How much percentage of the work, ‘B’ alone can c...
- If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
- 'A' is capable of completing a specific task on their own in 20 days. 'B' can independently handle 60% of the same task in 18 days. If 'A' and 'B' collabor...
- A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece of...
- The ratio of time taken by P, Q and R to complete work alone is 6:8:4 respectively. If all three together complete the work in 8 days, then find in how man...
- 'P', 'Q', and 'R' can individually complete a task in 20, 24, and 30 days, respectively. They all started working together, but 'P' stopped after 4 days. A...
- A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the ef...
- Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops aft...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)