Question
‘A’ alone can complete a work in 15 days while ‘A’ and ‘B’ together can complete the same work in 10 days. How much percentage of the work, ‘B’ alone can complete in 21 days?
More Time and work Questions
- P, Q and R together can complete a task in 12 days. Q and R together can finish it in (72/5) days, and R alone can do half the task in 8 days. What is the ...
- A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then find t...
- ‘Pooja’ alone can finish a piece of work in 60 days. After working for 36 days, she left the job. ‘Vikram’ then completed the rest in 12 days. How many day...
- Anoop and Bhanu together can finish a certain piece of work in 90 days, while Bhanu and Charu together can complete the work in 70 days. Bhanu, Charu, and ...
- A and B together, B and C together and A and C together can complete a piece of work in 12 days, 11 days and 9 days respectively. Find the ratio of the eff...
- Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops aft...
- A can complete a work in 18 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 50% of the work...
- P and Q together finish a piece of work in 12 days. R works at half the efficiency of P. Q alone can finish the work in 30 days. Now if Q and R work togeth...
- 'A' and 'B' alone can complete a work in 14 days and 21 days, respectively. Find the time taken by them to complete the work if they work on alternate days...
- 12 men working for 6 hours a day can complete a work in 20 days. If 30 women are employed to work, then find how many hours a day they have to work to comp...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)