A can complete a piece of work in 24 days. A does the work in 24 days =1 A does the work in 1 day =1/24 A does the work in 21 days = (1/24) ×21=7/8 Remaining work =1-7/8 =1/8 Remaining work finished by B in 6 days =6×8=48days. A and B together finish the work – 2448 96 42 =96/4+2 =96/6 =16 days.
Consider the following statements aboutGreen rising initiative:
1. Recently, UNESCO in collaboration with India's Ministry of Environment...
How much of the Brics + export share was contributed by China in 2023?
Which company is collaborating with IIT Madras to build Asia's first Hyperloop test track?
Which of the following statements is/are incorrect?
I. Recently a Portal named “SAMBHAV” has been launched by Madhya Pradesh.
...What is the amount of financial support announced by the Board of Control for Cricket in India (BCCI) to the Indian Olympic Association (IOA) for the 20...
Which country recently honored Sri Sri Ravi Shankar with its highest civilian award?
___________ is set to represent India at the Commonwealth Games 2022 after securing a gold medal in the 55 kg category by lifting a total of 191 kg in t...
UPI volume cap deadline extended till _______.
Which Indian American has been named as the Deputy CEO of the US Finance Agency?
Which company received final authorization from RBI to act as a payment aggregator in August 2024?