πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Month End Offer - Flat 52% Off On All Courses! Enroll Now ⚑
    00:00:00 AM Left

    Question

    A can complete a piece of work in 24 days. He worked for

    21 days and then B finished the remaining work in 6 days. In how many days can A and B finish the work together?
    A 12days Correct Answer Incorrect Answer
    B 15days Correct Answer Incorrect Answer
    C 16days Correct Answer Incorrect Answer
    D 18days Correct Answer Incorrect Answer

    Solution

    A can complete a piece of work in 24 days. A does the work in 24 days =1 A does the work in 1 day =1/24 A does the work in 21 days = (1/24) Γ—21=7/8 Remaining work =1-7/8 =1/8 Remaining work finished by B in 6 days =6Γ—8=48days. A and B together finish the work – 2448 96 42 =96/4+2 =96/6 =16 days.

    Practice Next
    More Time and work Questions
    ask-question