πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug ⚑ Enroll Now

    Question

    A and B can complete a task together in 24 days, while B

    alone takes 48 days to finish it. A began working alone and left after β€˜x’ days, after which B completed the remaining work in 36 days. Determine the percentage of the total work completed by A.
    A 25% Correct Answer Incorrect Answer
    B 15% Correct Answer Incorrect Answer
    C 20% Correct Answer Incorrect Answer
    D 40% Correct Answer Incorrect Answer

    Solution

    Let total amount of work be 48 units
    Efficiency of (A + B) = 48/24 = 2 units/day
    Efficiency of β€˜B’ = 48/48 = 1 unit/day
    Amount of work done by β€˜B’ = 36 Γ— 1 = 36 units
    Percentage of work done by β€˜A’ = {(48 – 36)/48} Γ— 100 = 25%

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call