      Question

      X and Y together complete a job in 18 days, while Y

      alone can do it in 30 days. The ratio of efficiencies of X and Z is 4:5 respectively. What is the ratio of efficiencies of Y and Z?
      A 8:9 Correct Answer Incorrect Answer
      B 6:5 Correct Answer Incorrect Answer
      C 5:4 Correct Answer Incorrect Answer
      D 9:10 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let total work = 90 units {LCM of 18 and 30}

      Efficiency of (X + Y) = 90/18 = 5 units/day

      Efficiency of Y = 90/30 = 3 units/day

      Therefore, efficiency of X = 5 – 3 = 2 units/day

      Efficiency of Z = 2 Γ— (5/4) = 2.5 units/day

      Required ratio = 3 : 2.5 = 6 : 5