Question
12 men take 6 days to complete a piece of work. They
worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will be taken by them to complete the remaining work?Solution
12 men = 6 days Work done by 12 men in one day = 1/6 Work done by 12 men in 2 days = 1/6 × 2 = 1/3 Remaining work = 1 - 1/3 = 2/3 Now, 4 men joined them Therefore, 2/3 rd of work is done by 16 men in x days We have the formula, M1 × D1 / W1 = M2 × D2 / W2 Here, M1 = 12, D1 = 2 and W1 = 1/3 M2 = 16, D2 = x and W2 = 2/3 (12 × 2)/(1/3) = (16 × x)/(2/3) x = 3 days ALTERNATE SHORTCUT METHOD M1 × D1 = M2 × D2 12 × 6 = 12 × 2 + (12 + 4) × x 72 = 24 + 16 x 48 = 16 x So x = 3days
In the following letter set, the second letter set is related to the first letter set in a certain way, find the letter set from the options which is r...
986 : 53 : : 725 : ?
Select the option that is related to the third number in the same way as the second number is related to first number and the sixth number is related to...
Select the option that is related to third word in the same way as the second word is related to first word.
SETS : WAXO :: PORT : ?
Select the combination of the letters that when placed sequentially in the blanks of the given letter series will complete the series.
_ f _ g _ ...
If ASH = 1198 and ASHES = 1198519, then SQUASH =
Select the option that is related to the third word in the same way as the second word is related to the first word.
Chichen Itza : Mexico :: ...
‘Insect’ is related to ‘Larva’ in the same way as ‘Pig’ is related to ____.
Toyota’ is related to ‘Japan’ in the same way ‘Samsung’ is related to “___”.
Select the option that is related to third letter cluster in the same way as second letter cluster is related to first letter cluster.
DEL: IJQ :: OIL: ?