Question
12 men take 6 days to complete a piece of work. They
worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will be taken by them to complete the remaining work?Solution
12 men = 6 days Work done by 12 men in one day = 1/6 Work done by 12 men in 2 days = 1/6 × 2 = 1/3 Remaining work = 1 - 1/3 = 2/3 Now, 4 men joined them Therefore, 2/3 rd of work is done by 16 men in x days We have the formula, M1 × D1 / W1 = M2 × D2 / W2 Here, M1 = 12, D1 = 2 and W1 = 1/3 M2 = 16, D2 = x and W2 = 2/3 (12 × 2)/(1/3) = (16 × x)/(2/3) x = 3 days ALTERNATE SHORTCUT METHOD M1 × D1 = M2 × D2 12 × 6 = 12 × 2 + (12 + 4) × x 72 = 24 + 16 x 48 = 16 x So x = 3days
Select the option that arranges sentences A, B, C and D in a logical sequence.
A. Her first trip was in 1996 as a third year college student.
...Which of the following will be the THIRD sentence after rearrangement?
Given below are four jumbled sentences. Select the option that gives their correct order.
A. However, in Europe and the western world, there is a...
Five statements are given below labelled 1), 2), 3), 4) and 5). Among these, four statements are in logical order and form a coherent paragraph/passage....
Which of the following would be the FIRST statement after rearrangement?
- Given below are four jumbled sentences. Select the option that gives their correct logical sequence.
A. It is through the microscope’s lenses tha... Which of these should be the FIRST sentence after rearrangement?
Which of the following is the first sentence after rearrangement?
Sentences of a paragraph are given below in jumbled order. Arrange the sentences in the correct order to form a meaningful and coherent paragraph.
...Given below are four jumbled sentences. Select the option that gives their correct order.
A. They were not there ahead of him.
B. He tu...