A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 60% of the ...
X, Y and Z can do a piece of work in 90 days, 40 days and 120 days respectively. If they all work together alternatively starting with X, Y than Z respe...
‘A’ and ‘C’ together can dig a hole in 8 hours while ‘A’, ‘B’ and ‘C’ together can dig the same hole in 6 hours. Find the time taken...
A group of 16 women can complete a certain job in 48 days, working 7 hours each day. How many women would be required to complete the same job in 32 day...
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
A buffalo alone can plough field ‘A’ in 80 days. A Bull alone can plough the field ‘A’ in 160 days. Find the number of days taken by 2 bulls and...
7 men and 4 boys can complete a work in 6 days. A man completes double the work than a boy. In how many days will 5 men and 4 boys complete the work?
'A' and 'B' can together complete a job in 15 days. If 'B' alone can finish 50% of the job in 20 days, how long would it take 'A' alone to complete the ...
A can do a work in 16 days and B can do the same work in 12 days. How long will it take for A and B to complete the work if they work together?