Ravi and Sunil can complete a task in 12 days and 30
days respectively. Ravi started the task alone. After how many days should Sunil join him so that the task is completed in 10 days?Solution
ATQ,
Let the total work be 60 units (LCM of 12 and 30)
Efficiency of Ravi = 60 / 12 = 5 units/day
Efficiency of Sunil = 60 / 30 = 2 units/day
Let the time after which Sunil joined be n days.
So,
5n + (5 + 2) Ă— (10 - n) = 60
5n + 70 - 7n = 60
-2n = -10
n = 5
Which country secured the first position in the Global Fish Production 2022?
 Bandhan bank has roped _________ as its brand ambassador for the bank’s product and service endorsement.
What constitutes an unclaimed deposit according to the revised RBI guidelines?
Which class of algae is commonly known as brown algae?
Which Gharana is famous for Sitar players?
When do we observe National Doctors Day annually?
Which freedom fighter from Uttar Pradesh is known as the 'Iron Man of India'?
When did the Portuguese capture Goa from the Bijapur Sultanate?
What was the theme of National Voters’ Day this year?
Who is the Minister of Defence?