Question
A, B and C alone can do a certain piece of work in 15 days, 20 days and 30 days respectively. All of them started work together but after 'x' days, B and C left the job. Now, the remaining work is done by A with 50% more efficiency. Find the value of 'x', if the whole work is completed in '2x + 5' days.
More Time and work Questions
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- The time taken by ‘A’ to build a wall alone is 45% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
- A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then find t...
- A and B together can complete a piece of work in 12 days. A alone can complete the work in 20 days. A starts the work and is joined by B after 5 days. How ...
- A can do a piece of work in 28 days, while B can do the same piece of work in 42 days. They begin working together and 6 days before completion of work, A ...
- A, B and C can complete a project individually in 15 days, 20 days and 30 days respectively. They start working together, but C leaves after working for 2 ...
- Sufficient food-supply was arranged to last for 30 days for 250 soldiers. If 50 soldiers did not attend the camp, for how many extra days will the food-sup...
- A can complete a piece of work in 12 days and B can complete it in 18 days. They work together for 4 days and then B leaves. In how many more days will A f...
- 30 men can complete a piece of work in 11 days. 15 men started the same work and worked for 8 days, and then joined by ‘x’ more men such that the remaining...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)