Question
(x + 7) workers finish 60% of a job in 9 days working 4
hours/day. The remaining work is done by (x + 3) workers in 12 days working 3 hours/day. Find x.Solution
According to the question,
{(x + 7) ร 9 ร 4}/0.60 = {(x + 3) ร 12 ร 3}/0.40
Or, 2x + 14 = 3x + 9
Or, x = 5
Hence, value of x is 5.
Trashing, Arrowing and Ratooning are common practices in
The Cabinet Committee on Economic Affairs has approved Fair and Remunerative Price (FRP) of sugarcane as ____ (Rs/quintal) for sugar season 2022-23.
To prevent erosion in hills
When was the Pradhan Mantri Matsya Sampada Yojana (PMMSY) launched?
For the process of cDNA synthesis, the eukaryotic ___ is used as the template for the generation of ย DNA.ย
Velamen is the multi-layered epidermis formed in the aerial roots of
Inulin is a polymer of
Marginal utility of money cannot be:
According to Agricultural Statistics 2021-22, the state which is leading producer of rice isย
The CCEA has approved the Minimum Support Prices for all Rabi Crops for Marketing Season 2023-24. What is the MSP of Wheat?