Question
‘D’ alone can complete a task in 20 days. ‘E’ is 40% less efficient than ‘D’. They worked together for 5 days, after which ‘D’ stopped working. What percentage of the total work was completed by ‘E’?
More Time and work Questions
- Lucas, Maya, and Riley can build a wall in 5, 10, and 15 days respectively. If they start the job together and Lucas leaves 3 days before the job is done, ...
- 3 men and 1 boy together can complete a work in 20 days. 2 men and 3 boys can together complete half of the same work in 10 days. Find the time taken by 1 ...
- 28 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- ‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the task alone?
- Person A is 80% more efficient than person B. A and B together can complete a certain task in 10 days, while B and C together can complete the same task in...
- 'A' can complete a certain task in 60 days, while 'B' can do the same in 45 days. 'A' starts the task and works alone for 18 days, after which 'B' joins hi...
- Aman can complete a task in 24 days, while Bhavna can finish the same task in 40 days. How long will it take for Chetan to finish the task if his efficienc...
- The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by...
- A, B and C can complete a work in 15, 20 and 30 days respectively. They all start working together. After 3 days, C leaves. The remaining work is completed...
- A and B can complete a work in 12 days and 16 days, respectively. They start working together, but after 4 days, A leaves the work. C joins B, and they com...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt