Let the total work = 360 units Then, efficiency of ‘A’ = (360/40) = 9 units/hour Work completed by ‘A’ alone in 20 hours = 9 × 20 = 180 units Remaining work = 360 – 180 = 180 units So, efficiency of ‘B’ = 180/20 = 9 units/hour Therefore, combined efficiency of ‘A’ and ‘B’ = 9 + 9 = 18 units/hour So, time taken by ‘A’ and ‘B’ together to complete the work = (360/18) = 20 hours
Find the square root of 0.0324.
A horse is tethered to a peg with a 28 metre long repeat the corner of a 45 metre long and 25 metre wide rectangular grassfield. What area of field does...
Solve the following :-
Find the Square root of √17424
Find the Square root of √2116
What is the square root of 5476?
Find the Square root of √1681
Find the square of 572
If the average of two numbers is 13 and the square root of their product is 12, then the difference between the numbers is: