Question
‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 40 hours. If ‘B’ completed the rest of the work in 10 hours then find the time taken by ‘A’ and ‘B’ together to complete the whole work.
More Time and work Questions
- A alone can complete a work in 20 days and B alone in 30 days. A works alone for 10 days and then B joins him. In how many total days will the work be comp...
- It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 day...
- Worker ‘P’ can complete a job in 30 days, and together with ‘Q’, they can finish it in 12 days. If ‘Q’ worked alone for 15 days and then stopped, how long ...
- 36 women can complete a task in 20 days. If 18 women start the task and after 15 days ‘y’ more women join, ensuring the remaining work is completed in anot...
- The speeds of Vishank and Karun are 60 km/hr and 90 km/hr. Initially, Karun is at a point P and Vishank is at a place Q. The distance between P and Q is 13...
- A, B, and C are three workers who can complete a certain piece of work. A alone can complete the work in 12 days. B alone can complete the same work in 3X ...
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
- 12Men and 12women can complete a piece of work in 9 days. 6 men and 15 women can complete the same work in 12 days. How long (in days) would it take 9 wome...
- A team leader can do a job as fast as three members of the team working together. If one of the member can do the job in 5 hrs, the second one takes 10 hrs...
- 'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency whil...