Question
A fence is constructed using 900 wooden planks. ‘X’
alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes. ‘Z’, a curious kid, removes 4 planks per minute. If all three work together, how long will it take to finish the fence?Solution
ATQ,
Efficiency of ‘Y’ = (900 / 100) = 9 planks/minute So, combined efficiency of ‘X’, ‘Y’ and ‘Z’ = 10 + 9 – 4 = 15 planks per minute So, time taken to build the fence = (900 / 15) = 60 minutes = 1 hour
Consider the following Statements about:
             I.       Agriculture, Mining & quarrying are part of Primary Secto...
SDG India Index 2023-24, the _____ edition of the country’s principal tool for measuring national and subnational progress on the Sustainable Developm...
Which of the following statements are True about various types of Deposits?
I- Demand deposits can be withdrawn at the wish of the depositor as t...
Jal Jeevan Mission ensures functionality of existing water supply systems and water connections, water quality monitoring and testing as well as sustain...
The headquarters of the European Investment Bank is situated in _______ ?
Which of the following government scheme is implemented through Life Insurance Corporation?
Who among the following is the implementing agency for Pradhan Mantri Shram Yogi Mandhan Yojana?
What should be the maximum income of a person for availing the benefit of PM Shram Man dhan Yojana?
As per the Census 2011, the total number of internal migrants in India is _________.
What is the rank of India in Gender Gap report?