Question
A and B together do a job in 12 days. A alone does it in 20 days. How many days for B alone?
More Time and work Questions
- ‘m’ painters can paint a house in 60 days. If the crew increased by 25 painters, they could finish in 40 days. What is the value of ‘m’?
- Shivam and Harish can do a job alone in 90 days and 120 days respectively. Both work together and earn Rs. 5,250. Find Shivam’s earnings.
- A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves. B co...
- Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can Deepak...
- (x + 9) laborers complete 45% of a task in 12 days working 5 hours/day. The rest is done by (x + 4) laborers in 18 days working 5 hours/day. Find x.
- Ajay alone can complete a work in 50 days. Vijay is four times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10...
- A can complete a piece of work in 16 days and B can complete it in 24 days. They work together for 4 days and then B leaves. In how many total days is the ...
- Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the sa...
- 126 unit of work can be completed by P alone in 21 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- 'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while 'Ta...