Question
45 people can repair a road in 10 days working 6 hours a day. In how many days can 30 people working 6 hours a day complete the same work?
More Time and work Questions
- Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed the ...
- A can complete a piece of work in 12 days , and B can complete it in 18 days . They work together for 4 days , and then A leaves. In how many more days...
- A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for th...
- A and B together can complete a piece of work in 10 days. B and C together can complete it in 15 days, and A and C together can complete it in 12 days. All...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- A contractor assigned 18 laborers to complete a task in 16 days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to ...
- ‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1400, then fin...
- A, B, and C can individually complete a task in 20 days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after whi...
- Pooja is twice as efficient as Nita and four times as efficient as Kavya. If Nita takes 30 days to finish some work, then find the time taken by Pooja and ...
- ‘A’ is 50% less productive compared to ‘B’, who is 20% more productive than ‘C’. Together, they can finish a task in 36 days. After ‘B’ and ‘C’ have worked...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt