Question
A and B together can do a work in 10 days, B and C can
do together in 5 days while C and A together can do in 12 days. In how many days C alone will complete the work?Solution
(A + B)’s 1 day’s work = 1/10 (B + C)’s 1 day’s work = 1/5 (C + A)’s 1 day’s work = 1/12 2 (A +B + C)’s 1 day’s work = 1/10 + 1/5 + 1/12 = (6+12+5)/60 = 23/60 ∴ (A + B + C)’s 1 day’s work = 23/120 Now, C’s 1 day’s work = (A + B + C)’s 1 day’s work – (A + B)’s 1 day’s work, => 23/120 – 1/10 = 11/120 Therefore C will finish the work in = 120/11 =
days.
The choice between oral and written communication often depends on the nature of the message and the desired outcome. Which of the following situations ...
Which campaign did HDFC Life launch to simplify and speed up the life insurance purchase process?
Which of the following financial products can be traded in Gift City's exchanges?
1)Â Â Â Currency derivatives
2)Â Â Â Agricultural...
Consider the following statements:
1)India has the largest emigrant population and is the top remittance recipient country.
2)Remittances ...
The Assets Liabilities committee (ALCO) in a bank is primarily responsible for managing which of the following risk?
Which of the following methods for calculating the Maximum Permissible Bank Finance (MPBF) considers the permanent level of current assets, also known a...
Consider the following statements with reference to GIFT City:
1)Â Â Â GIFT City is a Special Economic Zone (SEZ) located in the state of Guj...
As per the recently published discussion paper on expected credit loss model for banks, loss allowances on lease receivables and contractual guarantees ...
The process of identifying and tracking high-potential employees who will be able to fill top management positions when they become vacant is known as
What is the purpose of the Clearing Corporation of India Limited (CCIL) in the Indian capital market?