Question
Working individually, 'A' can finish 60% of a task in 18
days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' working together can complete the task in 20 days. Now, What will be the amount of time 'C' would need to complete the same task when working alone.Solution
ATQ, Time taken by 'A' alone to complete the entire work = 18 ÷ 0.6 = 30 days Time taken by 'B' alone to complete the entire work = 30 + 15 = 45 days Let the total work = L.C.M of 30, 45 and 20 = 180 units Then, efficiency of 'B' = (180/45) = 4 units/day Combined efficiency of 'B' and 'C' = (180/20) = 9 units/day So, efficiency of 'C' alone = 9 - 4 = 5 units/day So, time taken by 'C' alone to complete the entire work = (180/5) = 36 days
Shrilal Joshi is a famous painter of-
- The 'Doctrine of Lapse' was introduced by which Governor-General of India?
The receipts which neither create any liability nor reduce any asset are called ______.
Forest research Institute of India is situated in?
Who is credited with the discovery of penicillin?
- Which Indian state has the largest forest cover by area?
Where is the High Court of Orissa located in the state?
As per the Economic Survey of India 2021-22 report (as per advance estimates), the service sector has contributed nearly ____of India’s 2021-22 GDP.
Rock Inscription 'Ghosundi' is located at -
Which of the following is not correctly matched?