ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    тЪб Month End Offer - Flat 52% Off On All Courses! Enroll Now тЪб
    00:00:00 AM Left

    Question

    The team of A B and C was supposed to complete a piece

    of work. Working alone, A could have completed the same work in 190 hours. B could have completed the same work in 285 hours, while C could have completed it in 342hours.The trio decided that one of the three would work at any point of time. In the first cycle of three days A worked for two hours on Day 1, B worked two hours on Day 2, and C worked for two hours on Day 3. In the second cycle of three days A worked for four hours on Day 1, B worked for four hours Day 2, and C worked for four hours on Day 3.In the third cycle of three days A worked for six hours on Day 1, B worked for six hours on Day 2, and C worked for six hours on Day 3. This continued till the piece of work was completed. with each working for 2n hours in Cycle n, the sole exception┬а being made, if necessary, in the Last cycle, as the work may get completed midтАФcycle. What was the total number of days needed for the work to completed ?
    A 26.4 Correct Answer Incorrect Answer
    B 25.8 Correct Answer Incorrect Answer
    C 25.5 Correct Answer Incorrect Answer
    D 26 Correct Answer Incorrect Answer

    Solution

    The correct answer is D

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question