Question
The team of A B and C was supposed to complete a piece
of work. Working alone, A could have completed the same work in 190 hours. B could have completed the same work in 285 hours, while C could have completed it in 342hours.The trio decided that one of the three would work at any point of time. In the first cycle of three days A worked for two hours on Day 1, B worked two hours on Day 2, and C worked for two hours on Day 3. In the second cycle of three days A worked for four hours on Day 1, B worked for four hours Day 2, and C worked for four hours on Day 3.In the third cycle of three days A worked for six hours on Day 1, B worked for six hours on Day 2, and C worked for six hours on Day 3. This continued till the piece of work was completed. with each working for 2n hours in Cycle n, the sole exception being made, if necessary, in the Last cycle, as the work may get completed mid—cycle. What was the total number of days needed for the work to completed ?Solution
The correct answer is D
When a metal reacts with dilute hydrochloric acid, it produces:
Which of the following element is required for the conversion of the solar energy?Â
A battery of emf 12 V and internal resistance 4 ohm is connected to a resistor. If the current in the circuit is 0.6 A, what is the resistance of the re...
Which blood group is the universal recipient?
Deficiency of which vitamin leads to bleeding gums?
Natural radioactivity was discovered byÂ
What is the reason for twinkling of stars?
What is the most basic criteria used to decide whether something is alive?
The SI unit of mechanical power is:Â
The SI unit of surface tension is: