Question
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed the same work in 285 hours, while C could have completed it in 342hours.The trio decided that one of the three would work at any point of time. In the first cycle of three days A worked for two hours on Day 1, B worked two hours on Day 2, and C worked for two hours on Day 3. In the second cycle of three days A worked for four hours on Day 1, B worked for four hours Day 2, and C worked for four hours on Day 3.In the third cycle of three days A worked for six hours on Day 1, B worked for six hours on Day 2, and C worked for six hours on Day 3. This continued till the piece of work was completed. with each working for 2n hours in Cycle n, the sole exception being made, if necessary, in the Last cycle, as the work may get completed mid—cycle. What was the total number of days needed for the work to completed ?
More Time and work Questions
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- 'Aman' and 'Bhanu' together can complete a work in 7.2 days. Both of them started the work but 'Bhanu' left the work after 3 days and remaining work was co...
- A is five times as efficient as B and can finish a piece of work in 24 days less than B. B can finish this work in how many days?
- A and B together can do a work in 12 days. If A can alone do the same work in 18 days, then in how many days B alone will do the same work?
- Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start Kara...
- A takes twice as much time as B and thrice as much time as C to finalize a task. Working together, they can complete the task in 8 days. The time (in days)...
- A can finish a piece of work in 12 days, B in 15 days. They work together for 4 days, then A leaves and C joins B. C is 25% more efficient than B. In how m...
- X and Y can complete a work in 12 days and 10 days respectively. With the help of Z, X and Y together can complete the work in 5 days for a total salary of...
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- Shivam and Harish can do a job alone in 90 days and 120 days respectively. Both work together and earn Rs. 5,250. Find Shivam’s earnings.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt