Question
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed the same work in 285 hours, while C could have completed it in 342hours.The trio decided that one of the three would work at any point of time. In the first cycle of three days A worked for two hours on Day 1, B worked two hours on Day 2, and C worked for two hours on Day 3. In the second cycle of three days A worked for four hours on Day 1, B worked for four hours Day 2, and C worked for four hours on Day 3.In the third cycle of three days A worked for six hours on Day 1, B worked for six hours on Day 2, and C worked for six hours on Day 3. This continued till the piece of work was completed. with each working for 2n hours in Cycle n, the sole exception being made, if necessary, in the Last cycle, as the work may get completed mid—cycle. What was the total number of days needed for the work to completed ?
More Time and work Questions
- The ratio of time taken by P, Q and R to complete work alone is 4:5:2 respectively. If all three together complete the work in 8 days, then find in how man...
- A, B and C are hired at Rs 1050 to do a piece of work. A and B together complete 19/23 part of the work. And B and C together complete 8/23 of the work. Th...
- Ananya and Riya can complete a task in 20 hours and 40 hours respectively. Ananya works alone for 10 hours and then Riya finishes the remaining task. How l...
- P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how many ...
- A and B can each finish a task in 32 days and 36 days respectively. They begin the task together, but after 12 days, A leaves. How long will it take for B ...
- ‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 2...
- 25 men can complete a piece of work in 30 days. ‘x’ men started the work and after 24 days 60 more men joined them so that whole work was finished in the d...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 20 days. 'A' started the work alone and worked on...
- A can complete a task 40% more efficiently in 25 days, whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at th...
- The efficiency of C is 20% more than the efficiency of D. D alone can complete a piece of work in (y-2) days. The time taken by C alone to complete the wor...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)