Question
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed the same work in 285 hours, while C could have completed it in 342hours.The trio decided that one of the three would work at any point of time. In the first cycle of three days A worked for two hours on Day 1, B worked two hours on Day 2, and C worked for two hours on Day 3. In the second cycle of three days A worked for four hours on Day 1, B worked for four hours Day 2, and C worked for four hours on Day 3.In the third cycle of three days A worked for six hours on Day 1, B worked for six hours on Day 2, and C worked for six hours on Day 3. This continued till the piece of work was completed. with each working for 2n hours in Cycle n, the sole exception being made, if necessary, in the Last cycle, as the work may get completed mid—cycle. What was the total number of days needed for the work to completed ?
More Time and work Questions
- ‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 2...
- "Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but Bhanu stops after 4 days, a...
- Ratio of the work done by P, Q and R in one day is 5:4:8 respectively. They all together can complete the work in 40 days. Q and R worked on it for 20 days...
- X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the task i...
- Rahul can complete a project in 50 days, while Karan can finish the same project in 75 days. Rahul starts working alone, and after 30 days, Karan joins him...
- A can complete a piece of work in 10 days. B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many da...
- A alone can complete a piece of work in 12 days, and B alone can complete it in 18 days. They work together for 4 days, after which A leaves. In how many t...
- Vijay can do a piece of work in 34 days and Sanjay can do the same work in 51 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work will...
- Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu join...
- Efficiency of a man is 50% more than that of a woman. (n - 10) men working 6 hours a day can complete a task in 15 days, whereas (n - 9) women working 6 ho...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)